06 Aug - 8 min read

Alphamin announces Q2 2021 EBITDA of US$34,1m at a tin price of US$28,308/t (current: US$34,700/t)

Alphamin announces Q2 2021 EBITDA of US$34,1m at a tin price of US$28,308/t (current: US$34,700/t)

Alphamin Resources Corp.
Continued in the Republic of Mauritius
Date of incorporation: 12 August 1981
Corporation number: C125884 C1/GBL
TSX-V share code: AFM
JSE share code: APH
ISIN: MU0456S00006
(“Alphamin” or the “Company”)

       ALPHAMIN ANNOUNCES Q2 2021 EBITDA OF US$34,1m AT A TIN PRICE OF
                      US$28,308/t (Current: US$34,700/t)

MAURITIUS – August 6, 2021 – Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX,
“Alphamin” or the “Company”), a producer of 4% of the world’s mined tin1 from its high grade
operation in the Democratic Republic of Congo, has released its unaudited consolidated
financial statements and accompanying Management’s Discussion and Analysis for the three
and six months ended June 30, 2021:

- Q2 EBITDA of $34,1m, at a tin price of $28,308/t versus current of $34,700/t
- Net Debt reduced to $29,5m
- Contained tin production of 2,412 tons (11% below prior guidance and 8% below the
  prior quarter)
- Fine tin recovery plant fully commissioned and producing from 26 June 2021
- Mpama South phase 3 drilling progressing to plan with high-grade intercepts previously
  announced
- Mpama North Deeps drilling commenced with additional rigs under mobilisation to
  accelerate drilling campaign

Operational and Financial Summary for the Quarter ended June 20212

    Description                      Units                        Actual
                                                  Quarter        Quarter
                                                ended June         ended         Variance
                                                   2021         March 2021
    Tons Processed                   Tons         105,294          93,997          12%
    Tin Grade Processed              % Sn            3.2             3.8          -16%
    Overall Plant Recovery            %               72              74           -3%
    Contained Tin Produced           Tons          2,412           2,611           -8%
    Contained Tin Sold               Tons          2,404           3,351          -28%
    EBITDA                         US$'000        34,077           36,453          -7%
    Tin Price Achieved              US$/t         28,308           23,083          23%
    AISC per ton tin sold           US$/t         15,112           12,162          24%

________________________________________________________________________________________
1
 Data obtained from International Tin Association Tin Industry Review 2020 2 Production information is disclosed on a 100%
basis. Alphamin indirectly owns 84.14% of its operating subsidiary to which the information relates.

Operational and Financial Performance
Contained tin production of 2,412 tons was 11% below guidance (2,700 tons), impacted by a
low feed grade of 3.2% Sn compared to 3.8% Sn the previous quarter. The month of June
2021 saw lower than expected grades from underground. The variable nature of high-grade
tin mineralisation in the orebody may cause large fluctuations in delivered grade – as a
mitigating tool we will increase planned waste development for the remainder of the year in
order to provide more mining flexibility for blending high- and low-grade areas.

Taking into consideration the lower feed grade, the processing plant performed well, treating
12% more material and achieving recoveries of 72%.

Our EBITDA of $34,1m for Q2 2021 is 7% below Q1 2021 – the previous quarter benefitted
from a significant catch-up in tin sales following logistical bottlenecks during Q4 2020. Tin
prices are currently trading at around $34,700/t, 23% above prices achieved during the past
quarter.

Net debt amounted to $29,5m at 30 June 2021, down 50% from the start of the financial year
(31 December 2020: $59,9m).

The Company has appointed Mr. Jan Trouw as the on-mine Managing Director of its 84,14%
subsidiary, Alphamin Bisie Mining, effective 1 July 2021. Mr Trouw is well known to the
Alphamin team and has over 40 years of African mining experience – recently as head of the
Frontier copper mine in the DRC and prior to that as General Manager of the high-grade
Chibuluma copper mine in Zambia. He was instrumental during late 2019 as an advisor in
developing the new mining method and mine design criteria for Alphamin’s Bisie tin mine. We
look forward to working with Mr Trouw in realising our vision of becoming one of the world’s
largest long-life tin producers.

Over the last 7 years, Alphamin’s Bisie tin mine has developed from an exploration asset to a
steady state operating mine, producing 4% of the world’s mined tin. Our Chief Operating
Officer, Mr Trevor Faber, was instrumental in delivering on this key objective with exceptional
drive under challenging conditions. By mutual agreement, Mr Faber and the Company resolved
that it’s Bisie mine is in safe hands under the on-mine leadership of the Managing Director, Mr
Trouw, and his team. Therefore Mr Faber’s role as corporate Chief Operating Officer is no
longer required with effect 5 August 2021. The Board wishes to express its sincere gratitude
to Mr Faber for a job well done and looks forward to following his future successes in
developing the next major project.

Guidance for H2 2021

The grade of ore mined from underground in Q2 2021 was lower than that expected from the
Mineral Resource model, although some benefit was gained from additional tin mineralisation
delineated by grade control drilling. Overall, for material mined since commissioning to date,
the actual grades from underground were substantially in line with the Resource Model after
taking account of planned dilution factors.

Underground practices relating to stope planning, delineation and blasting were sub-optimal
during H1 2021. Our newly appointed ABM Managing Director, Jan Trouw, has already
introduced much improved planning and mining practices with positive results.

For the second half of 2021 and into Q1 2022, we expect to mine lower tin grades averaging
3,2% to 3,5%, which at higher plant recoveries of 78% (including the FTP recovery) and
monthly throughput of 36,000t amounts to contained tin production of between 900t and 1000t
per month. Production guidance for H2 2021 is approximately 5,500t of contained tin (previous
guidance: 6,500t). The grade of ore mined is expected to increase to an average of 4% from
Q2 2022 leaving this lower grade window as temporary.

Growth Initiatives

Fine Tin Recovery Plant (FTP) - The FTP is fully commissioned and has produced at steady
state from 26 June 2021. Expenditure at completion amounted to US$5.7 million. Production
from the FTP since commissioning increased overall contained tin production by 5%. This
exceeded expectations so early after commissioning. Optimisation work in pursuit of higher
FTP recoveries is ongoing.

Exploration Activities - Alphamin’s exploration initiative aims to: extend the life-of-mine at its
currently producing Mpama North operation; to declare a Maiden Mineral Resource for Mpama
South (located 750 metres south of Mpama North); and to discover at least one additional
orebody on the highly prospective Bisie Ridge (13km strike length).

Drilling at the Mpama North orebody commenced on 2 July 2021. An initial 15,000 metre (22
holes) drilling campaign over 4 months is planned to test the strike and dip extension of the
current producing orebody, below 400m in depth from the mine portal.

The initial Mpama South drilling program comprises of 16,800m of which 12,300m (52 holes)
has been completed. Independent laboratory assays have been received for 39 holes to date.
This initial drilling program is intended to form the basis of a Mineral Resource estimation
exercise, the results of which are expected to be announced by the end of 2021. Infill drilling
and further step-out drilling will continue from after August for the remainder of 2021. As
previously announced, drilling results to date indicate the potential for another high-grade
deposit, 750m South of the Company’s current producing Mpama North mine.
In addition to Mpama North and Mpama South, drilling on the highly prospective Bisie ridge
(13km strike length), which falls within the Company’s mining licence, is expected to
commence during Q3 2021. The Company’s appointed structural specialists, TECT Geological
Consulting, identified high potential drill targets less than 8km south of the current operating
mine.

Covid-19 Pandemic and Impact on Operations

The health of our employees is of paramount importance and in this regard the Company has
a range of Covid-19 awareness, prevention and other risk mitigation controls in place.

To date, the Company has been able to continue with normal production and concentrate sales
activities and has not been negatively affected by the Covid-19 pandemic.

Qualified Person

Mr. Clive Brown Pr. Eng., B.Sc. Engineering (Mining), is a qualified person (QP) as defined in
National Instrument 43-101 and has reviewed and approved the scientific and technical
information contained in this news release. He is a Principal Consultant and Director of Bara
Consulting Pty Limited, an independent technical consultant to the Company.
__________________________________________________________________________________________

FOR MORE INFORMATION, PLEASE CONTACT:

Maritz Smith
CEO
Alphamin Resources Corp.
Tel: +230 269 4166

E-mail: msmith@alphaminresources.com


The JSE link to the supporting document is
https://senspdf.jse.co.za/documents/2021/jse/isse/APHE/q22021.pdf.

JSE Sponsor
Nedbank Corporate and Investment Banking, a division of Nedbank Limited


CAUTION REGARDING FORWARD LOOKING STATEMENTS
Information in this news release that is not a statement of historical fact constitutes forward-
looking information. Forward-looking statements contained herein include, without limitation,
statements relating to expected future EBITDA for Q2 2021, the impact of the Company’s fine
tin recovery plant on production and the timing and success of additional exploration drilling
outcomes. Forward-looking statements are based on assumptions management believes to
be reasonable at the time such statements are made. There can be no assurance that such
statements will prove to be accurate, as actual results and future events could differ materially
from those anticipated in such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. Although Alphamin has attempted to identify important
factors that could cause actual results to differ materially from those contained in forward-
looking statements, there may be other factors that cause results not to be as anticipated,
estimated or intended. Factors that may cause actual results to differ materially from expected
results described in forward-looking statements include, but are not limited to: uncertainties
associated with Alphamin’s resource and reserve estimates, uncertainties regarding estimates
of the expected mined tin grades, processing plant performance and recoveries, uncertainties
regarding global supply and demand for tin and market and sales prices, uncertainties with
respect to social, community and environmental impacts, uninterupted access to required
infrastructure, adverse political events, impacts of the global Covid-19 pandemic on mining
operations and commodity prices as well as those risk factors set out in the Company’s
Management Discussion and Analysis and other disclosure documents available under the
Company’s profile at www.sedar.com. Forward-looking statements contained herein are made
as of the date of this news release and Alphamin disclaims any obligation to update any
forward-looking statements, whether as a result of new information, future events or results or
otherwise, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined
in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.

USE OF NON-IFRS FINANCIAL PERFORMANCE MEASURES
This announcement refers to the following non-IFRS financial performance measure:

EBITDA

EBITDA is profit before net finance expense, income taxes and depreciation, depletion, and
amortization. EBITDA provides insight into our overall business performance (a combination
of cost management and growth) and is the corresponding flow driver towards the objective of
achieving industry-leading returns. This measure assists readers in understanding the ongoing
cash generating potential of the business including liquidity to fund working capital, servicing
debt, and funding capital expenditures and investment opportunities.

This measure is not recognized under IFRS as it does not have any standardized meaning
prescribed by IFRS and is therefore unlikely to be comparable to similar measures presented
by other issuers. EBITDA data is intended to provide additional information and should not be
considered in isolation or as a substitute for measures of performance prepared in accordance
with IFRS.

Date: 06-08-2021 03:18:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.
Information on this Website is provided for general information purposes only and is not a substitute for professional advice. ASX Information (including company announcements and prices) is delayed by at least 20 minutes. JSE Information (including company announcements and prices) is delayed by at least 15 minutes. Reliance on the information you access on or from this Website is solely at your own risk. We make no representation or warranty in relation to the future performance of the companies that appear on this Website. Investment in securities involves risk and you should obtain independent professional legal, financial, investment or company advice before acting on any of the information you access on this Website. Using, browsing or otherwise accessing this Website is subject to our Terms and Conditions and our Privacy Policy.

© 2021 Listcorp. ABN 60 166 140 307

Never miss news from Alphamin Resources Corporation (JSE:APH) when you join Listcorp.